Skip to content

Shielded chamber, Meine

The shielded chamber in Meine complements the fully anechoic chamber with a separate test environment for development-stage investigations, diagnostics and the verification of optimisation measures.

Test setup in the shielded chamber operated by SAMD Solutions in Meine, with measurement equipment
Service
Complementary shielded test environment
Location
Meine, Lower Saxony
AC supply
single-phase, up to 16 A

Technical data sheet

Our two test environments together form the EMC capability portfolio of EMC Labs. The appropriate environment and test setup depend on the test method, device under test, supply requirements, setup and engineering question.

This page describes the equipment in Meine. The shared capability portfolio is set out under Two test environments, one capability portfolio.

AC supply
single-phase, up to 16 A
DC supply
up to 60 V, 10 A

We agree the test scope and the depth of assessment per project. If a question is a better fit for the other site, we say so – see Fully anechoic chamber, Harbke.

Address

SAMD Solutions GmbH
Peiner Straße 16
38527 Meine
Lower Saxony, Germany

Contact

Request a measurement slot
Near-field probe above a circuit board, next to a spectrum analyser

Typical use cases

  • Locating interference sources on the board or a cable instead of swapping parts on suspicion
  • Observing and documenting how the device behaves under transient disturbances
  • Measuring the effect of filter, shielding and grounding changes straight away
  • Preparing the setup and operating states for a later external test

Limits of the equipment

So that you know in advance what is not possible at this site:

  • The supply is limited to DC 0–60 V / 10 A and single-phase AC 16 A.
  • We do not state blanket figures for the internal dimensions, device size or frequency range – these are clarified per project.
  • We measure at the pre-compliance stage. These are not accredited tests.

How a measurement day runs

Four steps, repeated as often as the development work needs. You are welcome to be there all day.

  1. 1

    Arrive and set up

    You bring the device, its peripherals and its power supply. We set up together and record the setup with photos, so the measurement stays traceable later on.

  2. 2

    First measurement

    We measure the agreed scope and place the values against the relevant limits. You watch the curves as they appear.

  3. 3

    Narrow it down

    If something stands out, we change the setup deliberately: reroute a cable, insert a filter, add shielding. That turns a measured value into a cause.

  4. 4

    Re-measure

    We re-measure the effect of a change under the same conditions. You leave with documented values and concrete next steps.

What to bring

  • The device with its peripherals, loads and counterparts
  • The power supply as it looks in actual use
  • The operating states you want measured
  • Any anomalies you know of and existing measurement reports

The checklist sets this out in detail: Preparing your device for an EMC measurement.

Getting here and delivery

By car
The B 4 runs through Meine. It is about 7 km north of the Braunschweig-Nord interchange (A 2 / A 391); Braunschweig, Gifhorn and Wolfsburg are each roughly 10 km away.
Parking
We have our own parking spaces on site.
By train
The Meine stop is on the Braunschweig–Uelzen line and is served hourly by the RB 47.
Before you arrive
Please give us a quick call so someone is waiting for you at the test bench.
Address
Peiner Straße 16
38527 Meine

Frequently asked questions about Meine

Can I be there during the measurement?
Yes. You are welcome to be there throughout the day and watch the values as they appear. Someone who knows the device can switch operating states directly, which saves time.
What happens if a measurement stands out?
We narrow down the cause as far as the setup allows: scan the near field, reroute cables, try measures out and re-measure their effect.
Do I get an accredited test report?
No. Our measurements are pre-compliance and not accredited. They serve to spot anomalies early and to verify measures before a possible external test.
What power supply is available?
DC up to 60 V and 10 A, single-phase AC up to 16 A. If that is not enough for your device, we clarify beforehand whether the measurement is better placed in Harbke.

Request a measurement slot

You will receive a prompt response on the most suitable measurement option.